Building Project Update

Building Project Update May 2022Building Project Update February 2022
Building Update June 2021. Level 100: Work continues on the interior of the pool area Installation of new electric lines expected soon. Level 200: Ductwork and framing continues Plumbers installing piping and electricians continuing work. Level 300: Ductwork and framing continues Block walls, steel, and sheeting going in for the next level of this side of the building. Level 400: Block walls being installed that will support the steel he roof systemBUILDING UPDATE MAY 2021 ST. BERNARD-ELMWOOD PLACE CITY SCHOOLS 105 WASHINGTON AVENUE, ST. BERNARD, OH 45217 VISIT US AT SBEPSCHOOLS.ORG Soon we will begin seeing Level 400 exterior walls begin to go up. The bus loop will begin to be installed along Tower Ave. Ductwork for the HVAC system is being done throughout this level. Interior electrical work is being installed in the cafeteria Fire sprinkler system is being installed Interior work continues in this area The utility yard has been cut. Duke will soon remove utility poles so we can continue this work. LEVEL 200 LEVEL 400 LEVEL 100 Steel has been placed and Level 400 concrete floor has been poured. Plumbing and electrical installation for the High School cafeteria and serving area. LEVEL 300 WE HOPE TO ANNOUNCE OUR TRANSITION SCHEDULE SOON
BUILDING UPDATE APRIL 2021 UPDATES STILL TO COME ST. BERNARD-ELMWOOD PLACE CITY SCHOOLS 105 WASHINGTON AVENUE, ST. BERNARD, OH 45217 VISIT US AT SBEPSCHOOLS.ORG Soon we will begin seeing level 400 on the high school side steel going in for the flooring. A concrete slab will be poured on top the steel and then block walls will go up around the exterior of this level. Ductwork for the HVAC system is being done throughout this level. Framing for interior walls and interior plumbing is being installed. Gym walls have been dry-sealed. Block sealing will begin in this area once the weather begins to dry. LEVEL 200 LEVEL 400 LEVEL 100 Exterior block walls are being installed as well as concrete floors for the Elementary side. Concrete slabs have been poured for the High School cafeteria and serving area. LEVEL 300 WE HOPE TO ANNOUNCE OUR TRANSITION SCHEDULE SO
BUILDING UPDATE MARCH 2021 Non-bearing interior walls are being finished up Masonry will begin to erect exterior walls Interior pluming installation has began Air Handling System and Ductwork is bing installed in the Pool areal Plumbing and electric installation continues in the Pool area LEVEL 200 LEVEL 100 Footers and concrete walls have been poured Interior footers and elevator pit have been dug and poured for the Elementary LEVEL 300 UPDATES STILL TO COME: TITAN STAFF Classroom Technology Classroom + Office Set-Up What Can You Bring? TITAN COMMUNITY Monthly Building Updates Bell Schedule Plan Arrival + Dissmisal Times Traffic Flow Plan Bus Routes School Rules + Dress Code Update
BUILDING UPDATE FEBRUARY 2021, ST. BERNARD-ELMWOOD PLACE CITY SCHOOLS 105 WASHINGTON AVENUE, ST. BERNARD, OH 45217 VISIT US AT SBEPSCHOOLS.ORG Geopiers have been drilled and poured to support the building footers. The interior area of the Level 300 Elementary wing has been graded to height. Interior walls being built by masons. Steel beams will be set for flooring of the 300 level. Pool deck concrete was poured. Plumbing and electric installation continues in the Pool area. Updates still to come: TITAN STAFF Classroom Technology Classroom + Office Set-Up What Can You Bring? TITAN COMMUNITY Monthly Building Updates Bell Schedule Plan Arrival + Dismissal Times Traffic Flow Plan Bus Routes School Rules + Dress Code Update
Titan 

 

  Weekly Update

    June 15, 2020



 Construction site week of 06-15-20                           

The masons started on the north wall
of level 200 and laid all the block for
that side of the gym structure.  They
have now moved on to the west and
south walls and will continue to finish
the exterior walls of this part of the
building.  Steel will then be put in
place and a roof will be installed to
enclose the structure.

GeoPiers are being drilled, filled with
stone and compacted to establish the
base for footers on the educational
wing of level 200.  This part of the
building is on the east side or the side
closest to Tower Avenue.


Construction site week of 06-15-20


Construction site week of 06-15-20
Above Left: GeoPiers
Left:  Gym - Level 200
Right:North Gym Wall - Level 20

    Week of August 12, 2019
          • Level 100 footers for foundation

    Week of July 29, 2019
          • 100 Level excavation
          • Start footers
          • Continue storm work

    Week of July 22, 2019
         • Complete 100 level excavation
         • Continuing storm work


    Week of May 27, 2019
         • Complete backfilling trench from abatement
         • Complete 100 level excavation
         • Continue hauling dirt to level 300
         • Start footer and underground plumbing

    Week of May 20, 2019
         • All abatement will be completed
         • Begin backfilling trench from abatement
         • Completing 100 level excavation
         • Goal to get 100 level to sub grade
         • Hauling dirt to level 300
         • Start footers and underground plumbing


    Week of May 13, 2019

       
     • Continuing mass excavation of level 100 of building
         • Completing abatement


    Week of April 22, 2019
         • Continuing abatement of additional steam pipe
         • Continuing mass excavation of level 100 building pad

    Week of April 22, 2019
         • Abatement of steam pipe from boiler pit to high school
         • Continuing mass excavation of level 100 of building

    Week of April 1, 2019
         • Continue site clearing and excavation - concrete removal
         • Abatement of steam pipe
         • Begin excavation of level 100 of building
         • Approval of temporary stair at high school main entry


    Week of March 11, 2019
    After reviewing bids submitted by the February 20th closing date, Elevar Design Group, the project architect, has recommended that the construction contract for the St. Bernard-Elmwood Place pre-k-12 building be awarded to D.A.G. Construction, Inc.  The Board of Education will meet on March 11, 2019, to pass a resolution enabling the district to join with the Ohio Facilities Construction Commission in a contract with D.A.G., and construction is expected to begin in late March.


    Week of: February 11, 2019
    In order to accommodate more bids and expand the competition, St. Bernard-Elmwood Place School District has extended the bidding deadline for the new K-12 building project from January 31, 2019, to February 20, 2019, at 2 p.m.  This new date should increase the bidding pool and allow the district to get the most value for taxpayer dollars without significantly impacting the project completion date.


    Week of:  January 7, 2019
    A request for bids for the general construction portion of the new St. Bernard-Elmwood Place preK-12 facility was published on December 31, 2018.  The bids are due by electronic submission and will be opened at 2 p.m. on January 30, 2019.  The estimated base bid value is nearly $30 million, and there are several options with an additional estimated base bid value of just over $1 million.  Assuming bids submitted meet budget and expectations, construction should start in March of this year with a completion date prior to the end of the 2020-21 school year.  The Ohio Facilities Construction Commission continues to partner with the district to provide 82% of the funding for this project.



    Electronic bids will be received by St. Bernard-Elmwood Place City School District in conjunction with the Ohio Facilities Construction Commission for the following projects:
    Project SFC-170416
    New PreK-12 School
    St. Bernard-Elmwood Place City School District
    Tower Avenue
    St. Bernard, Hamilton County, OH 45217
    Please see link below for details:
    PK-12 Bid Notification Details


    Week of:  December 10, 2018
    The initial phase of the new building project, demolition of the old boiler house, has been completed.  Construction bids will go out this month, with the expectation that work will begin during the first quarter of 2019.


    Week of:  November 12, 2018

    The St. Bernard-Elmwood Place Schools will issue bids in December for a General Contractor to replace the current Construction-Manager-at-Risk in overseeing construction of the new preK-12 building project.  This change is expected to keep project costs within the approved budget. Project bidding will occur during the first quarter of 2019, with actual construction to begin the following quarter.


    Week of:  October 22, 2018
    With the completion and pending inspection of the boiler building removal project, St. Bernard-Elmwood Place City Schools are entering the next phase of the pre-K-12 building project.  At the recommendation of both the architectural firm, Elevar Design Group, and the Ohio Facilities
    Construction Commission, the district is proceeding with bidding to secure a general contractor.   The district plans to seek construction bids in December and January, months that historically have provided the most favorable bidding climate.  Construction will begin shortly after bids are accepted.  According to Elevar CEO, Tom Fernandez, “Not only will this project fall within the budget established by the Board of Education, but it will please the members of the community as well.”   Depending on final construction phasing plans, high school students could occupy the new building at the start of the 2020-21 school year, with elementary students following at a later date.


    Week of:  September 3, 2018
    The Board of Education approved the guaranteed maximum price (GMP#1) proposal for the demolition and abatement of the boiler building at its August 27, 2018, meeting.  Notice to proceed will be issued this week, with construction services and abatement activities scheduled to begin the week of September 17th.  Once negotiations are completed, the guaranteed maximum price (GMP#2) proposal for the new building construction will be presented for board approval in October.


    Week of: August 17, 2018
    The Board of Education will consider the guaranteed maximum price (GMP) proposal for demolition and abatement of the boiler house at its August meeting.  With board approval, demolition activities will begin September 18, 2018, and continue for four weeks.  The GMP for new building construction will be presented to the board for approval in early fall, so contraction should begin by mid-October.


    Week of: May 7, 2018
    With the design development budget reconciled, the construction development phase has begun. The "75% construction document set" was issued on May 1st to Elford, as Construction Manager. Elford is expected to issue the GMP (Guaranteed Maximum Price) in approximately six weeks.

    Once school is dismissed for the summer, demolition work and early site construction will begin. The design team has submitted drawings for the building permit and continues its work, focusing on finer details and coordination issues.

    Planning teams have begun another round of meetings among teachers, staff, and design team members. When school resumes in the fall, additional planning team meetings will be scheduled in anticipation of the bid package for furniture, finishes, and equipment.


    Week of: April 9, 2018
    The design development drawings and reconciled estimate were presented to the Board of Education and approved at their March 26th meeting. With the project entering the next phase, a 75%-complete construction document set is scheduled for issue by the end of April. The construction manager will provide the Guaranteed Maximum Price (GMP) six weeks later.

    Planning team meetings will resume before the current school year ends in late May. Demolition work and early site construction will begin in June. The design team will continue to meet on a regular basis, focusing on finer design details and coordination issues.


    Week of: March 5, 2018
    The design development drawings and preliminary estimate were presented to the Board of Education during its February meeting. Once the estimate is reconciled with the budget, that estimate will be presented to the Board of Education for approval at a special March meeting.

    As the project moves to the construction document phase, the design team will focus on finer details and coordination issues in the drawings. The planning team is scheduled to reconvene before the current school year ends.


    Week of: January 22, 2018
    The design development phase is entering the estimating stage, as the design team recently has submitted the provisional drawings and specifications for review and pricing by the construction manager. Over the next few weeks, the design and construction management teams will work closely with district leadership and the OFCC to reconcile the design development budget.  Once the budget is reconciled, the design development package will be presented to the Board of Education for approval.

    Following this approval, the construction document phase will begin. An early site construction package is expected to be issued in late spring. The planning team will reconvene before the current school year ends.


    Week of:  December 13, 2017
    Construction Update: Continuing in the design development phase, the design team has met with the various planning team groups during the past month. These groups have been updated on design progress since the last round of meetings. They have been provided with an overview of the elements to be included in the new building design, relevant to their various specialties, so that they could offer feedback.

    The design and owner teams have been working closely with the project engineering teams on both civil engineering and mechanical systems. In addition, food service and theatrical consultants have provided input to the design team.

    Upcoming milestone dates include the design development submittal in early 2018 and construction documents submittal in spring of 2018. The next round of planning team meetings will begin after the close of the design development phase in early 2018.


    Week of: October 30, 2017
    The new PK-12 school building is in the design development phase. The design team will resume meetings with the school planning teams the first week of November. In these sessions, teams will discuss details of the various building spaces.

    A public groundbreaking is scheduled for November 21st at 1:30 pm. The design development and construction document teams will submit plans before spring 2018.

    Week of: October 16, 2017
    The Design and Construction Management teams presented the schematic design and revised estimate for approval by the Board of Education at their September 27th meeting. With that approval, the project now enters the design phase.

    Design details will continue to be refined as the design team resumes meetings with the school planning teams. These planning team meetings will be scheduled during the last week of October and the first weeks of November.

    Upcoming milestone dates include the design development submittal in early 2018 and construction documents submittal in spring of 2018. A public groundbreaking ceremony is planned for November of this year.

    Week of: September 25, 2017
    The construction management and design teams are preparing the schematic design estimate for presentation to the Board of Education and OFCC at the September 27th Board of Education meeting. Civil, structural, architectural, mechanical, electrical, plumbing, technology, and food service planning are all part of these preparations. Once the Board of Education has approved the schematic design, the design team plans to resume meetings with the school planning teams.

    Design details will continue to be refined throughout the design development and construction phases. The building project remains on schedule for construction to begin in March 2018, with project completion in January 2020. A public groundbreaking ceremony is planned for November 2017.

    Week of: September 4, 2017
    The design and construction management teams are refining the schematic design estimate and are planning a presentation to the Board of Education in September. These teams are striving to make efficient use of the building site and to maintain a positive relationship with the new school's surrounding neighborhood.

    Once the Board of Education has approved the schematic design, the design team plans to resume meetings with the school planning teams in October. The building project remains on schedule for construction to begin in March 2018, with project completion in January 2020.

    Week of: August 14, 2017
    The construction management team is preparing its schematic design estimate for presentation to the Board of Education and the OFCC at the end of August. All facets of the design team are contributing to the estimations to ensure the design is on budget.

    Once the school year begins, the design team will resume meeting with the school planning teams. Details will continue to be refined throughout the design development process.

    A public groundbreaking ceremony is planned for November 2017.

    Week of: August 7, 2017
    Since the new school visioning sessions and planning team meetings in the spring, the design, construction, and administration teams have been working on school design and pre-construction site surveys. In early July, the construction team took soil samples, looked for foundation remains from the previous school buildings razed in the 1970s, and completed a traffic study.

    The design team continues to meet weekly over the summer. The schematic design was submitted at the end of June and is currently in the estimation phase.

    A public groundbreaking ceremony is planned for November 2017 in anticipation of construction beginning in the spring of 2018.


    07/22/19 – 8/5/19 - SBEP 2 week look ahead tasks:

    • Complete 100 level excavation
    • Continuing storm work

    07/22/19 – 8/5/19 - SBEP 2 week look ahead tasks:

    • Complete 100 level excavation
    • Continuing storm work